As an aid to the potential developer and self builder I will
be posting a site diary for each week that will show the stage's of the build
and the time they take to complete. I hope that this information will be of use
to you with your plan's.
Start New Project




As you can see from the plan & drawing this build consists of four two
bedroom apartments.
March 5th - 8th
- Site cleared
- Foundations Dug
- Concrete Poured



March 9th - 13th
Brick & Blockwork up to D.P.C level




March 14th - 16th
- Drainage
- Insulation
- Reinforcing
- Visqueen Membrane
- Concrete Floor Slab Layed
- Boundary Walls Started





March 17th
March 19th



April 20th
- First Floor Joist's fitted

April 27th
- Caberdeck Floor Fitted
- Brick and Block Ready to receive artstone cill's
- Ground Floor Partitions Started

May 12th
- Brick and Blockwork taken up to form 2nd floor window openings with
artstone head's above.
- Wall plate fitted to receive roof trusses.
- Scaffold due Monday.
- Crane due Tuesday to lift trusses into place.
- Landscaping started.

May 25th
- Girder Trusses in place to form 2nd floor bedrooms
- 2nd Floor Decked
- Facia's And Gutters
- Brick & Block Topout's Complete
- Boundry Walls Continued
- Roofer's Due Tomorrow






May 31st
- Roof Felted and tiled
- scaffold stripped
- window's and doors fitted
- Internal door frames and window boards fitted
- Balcony's due tomorrow


July 16th
- All Services Are Now Connected
- Kitchen's and Bathrooms Fitted
- Laminate Floors Layed
- After Final Decoration and Toppings to Driveways It Will Be Ready For
Occupation
- This Project Has Taken Four Months and This Includes Inclement Weather
That Stopped Production





New Projects Include This Drystone Gabion Retaining Wall

August 17th
Complete 1st floor extension to provide en-suite bedroom for expanding
family while still maintaining access to garage and garden's.

October 12th

Project now in the third week.
The Project is to convert the garage with attached leisure room into two
bedrooms with bathroom.
Also this project needs to be attached to the main house forming a dining room &
utility room.







October 26th
- Main Structural alterations complete.
- Roof Started.
- Windows and doors to be measured Monday.
- Electricians and plumbers to start midweek.