6th August
Natural stone detached bungalow. Self Managed by client.
- Project now into its third week.
- Foundations to D.P.C.
- Radon barrier fitted.
- Oversite concrete poured.
- Floor joists in position.
- Airbrick liners laid out.



15th August
- Stone up to sill height.
- Internal blockwork to lintel's.
- Scaffold due monday.




22nd August
- Stone Sills Fitted
- Corbels Formed
- Project Progressing To Schedule



29th August
- 2nd lift of scaffold erected.
- Internal door heads in place.
- External blockwork ready to receive joist.
- Stone heads fitted.
- Front and back to soffit hight.




10th September
- Ceiling Joist Fitted
- Spine walls Ready to Receive Timber Purlin's
- RSJ Purlin in place
- Ridge and Rafter Set
- Top Outs Started



15th September
Bungalow Topped Out.
Phase 1 Complete.


We will return to finish off after the scaffold is stripped.
Other works are planned for this site.
Building Progression to date

26th January
Site Works Start Again.